When we first contemplated living arrangements in Torrey, we knew restroom facilities would be a challenge. Luckily for us, there is a Texaco service station one mile from the yurt. Jesse, the owner of the Texaco station, didn’t seem to mind our daily visits, but some days that one mile seemed pretty far away. So one of the reasons for building the garage before the house was to provide a toilet and sink for ourselves and work crews plus any visitors that dropped by. Once the septic system was in, this became the next priority.
The interior of the garage was basically finished by the end of July: walls sanded and stained; man door in; outlets, switches, lights, garage door all installed. Three weeks ago we put up the interior walls of the bathroom and hung the door. Next we inserted insulation between the studs and put the exterior walls of the bathroom in place. All of this was done in anticipation of Phillip Winter’s arrival. (He’s our plumber.) We had previously arranged for him to put in two sinks - the porcelain sink in the bathroom and the salvaged stainless steel sink in the workstation in the southwest corner of the garage.
But we were going to purchase and set the toilet ourselves. And that’s where we hit our next snag. Phillip had placed the sewer hole for the toilet based on 2 X 4 construction. Our contractor had framed the bathroom using 2 X 6s. This mixup became apparent as we attempted to lower the toilet into position. The wall was too close to the hole! There wasn’t enough room for the toilet to fit!
After a conversation with Phillip, we learned this was a fairly common and easily solved problem. But, at the moment, it was no consolation since that meant the Texaco station was still in our future.
We spent the next week in Logan running errands which included returning the toilet. We didn’t have to explain to Lowe’s that it was too big. They just refunded our money...no questions asked. Meanwhile Phillip brought in a toilet that fit in a snug space. When we returned, we were very happy to see ...
It has been christened “The Texaco.”
Friday, August 28, 2009
The Saga of the Yellow Submarine
Long before Scott and I could even apply for a building permit, we made arrangements for a percolation test. This, of course, is required by the health department. The results of a percolation test inform the proper design of a septic system for the disposal of waste.
Last March, our friend Bruce, a soil scientist from across the mountain in Escalante, arrived with his tools and met Scott on our property. Scott Chestnut, our contact with a backhoe, was also there with his tool. Over the course of three days, he dug a test hole, and Bruce determined the level of the water table under our property to be about five feet. Below that, there was essentially a river flowing away to the south. The “river” didn’t seem to be a problem in as much as the footings for our house would be far shallower than that, and so would the septic system. Bruce wrote up his report, submitted it to the health department, and we received a certificate to file with our application for a building permit.
Next we met with Wes Jensen, the septic designer, and John Vercoe, the health inspector. Together we discussed and planned our soon-to-be-installed septic system. This would consist of many feet of drain pipe from the garage and house, gravel, a septic tank, and a drain field. As we headed back to Logan that week, we dropped off the required paperwork and planned to return to Torrey shortly in order to go ahead with the septic installation.
Two weeks later, we arrived back in Torrey and were greeted on site by a huge pile of gravel and a tall, corrugated, plastic septic tank which I immediately dubbed The Yellow Submarine because it was bright yellow. These were good signs. They meant Wes would be there in a day or two to put everything in the ground. Sure enough, that Thursday Wes and his assistant, Whitney, showed up with a little excavator and a load of pipe. They fired up the machine and began to dig. While they worked, Scott and I put finishing touches on the interior of the garage by sanding and staining the walls.
From our vantage point, we could see that, at first, everything was going well. But soon each shovelful of dirt was wetter than the previous one. When they brought mud out of the hole, we didn’t want to look anymore. Every now then, Wes would turn off the engine, and he and Whitney would stand beside the hole and scratch their heads. Finally, when they both threw their hands in the air, we knew it was time for us to wander over and take a peek at what had developed. It wasn’t a pretty sight.
The pile of dirt which, ideally, should have been dust dry, was, instead, an oozing mass of mud the consistency of day-old chocolate mousse. The hole which should have been just deep enough to hold the gravel and our yellow submarine was getting no deeper. Instead, it was rapidly getting wider, filling with water, caving in at the edges and creeping toward our future foundation site. Back in March, that flowing river was five feet down. Now it was two feet nearer the surface and eating away our septic hole chunk by eroding chunk. I had visions of our entire building site plus the pasture disappearing into an ever widening sink hole. The yellow submarine would never submerge. It would float forever in the pool rising at our feet.
That night Scott and I kept checking the slowly rising water. By morning the level was steady, and the hole had stopped growing, but it was obvious there was no possible way our new “swimming hole” would ever hold our septic tank. When people came by that day, we offered towels and bathing suits. If they declined, there was still a photo opportunity with the yellow submarine.
In the end, it took extra time and, of course, more money, but Wes found a solution. He pumped out the water, filled in the original hole, brought in a shallower septic tank (more of a black lozenge this time), quickly dug a new hole and got the entire system in without another hitch.
Last March, our friend Bruce, a soil scientist from across the mountain in Escalante, arrived with his tools and met Scott on our property. Scott Chestnut, our contact with a backhoe, was also there with his tool. Over the course of three days, he dug a test hole, and Bruce determined the level of the water table under our property to be about five feet. Below that, there was essentially a river flowing away to the south. The “river” didn’t seem to be a problem in as much as the footings for our house would be far shallower than that, and so would the septic system. Bruce wrote up his report, submitted it to the health department, and we received a certificate to file with our application for a building permit.
Next we met with Wes Jensen, the septic designer, and John Vercoe, the health inspector. Together we discussed and planned our soon-to-be-installed septic system. This would consist of many feet of drain pipe from the garage and house, gravel, a septic tank, and a drain field. As we headed back to Logan that week, we dropped off the required paperwork and planned to return to Torrey shortly in order to go ahead with the septic installation.
Two weeks later, we arrived back in Torrey and were greeted on site by a huge pile of gravel and a tall, corrugated, plastic septic tank which I immediately dubbed The Yellow Submarine because it was bright yellow. These were good signs. They meant Wes would be there in a day or two to put everything in the ground. Sure enough, that Thursday Wes and his assistant, Whitney, showed up with a little excavator and a load of pipe. They fired up the machine and began to dig. While they worked, Scott and I put finishing touches on the interior of the garage by sanding and staining the walls.
From our vantage point, we could see that, at first, everything was going well. But soon each shovelful of dirt was wetter than the previous one. When they brought mud out of the hole, we didn’t want to look anymore. Every now then, Wes would turn off the engine, and he and Whitney would stand beside the hole and scratch their heads. Finally, when they both threw their hands in the air, we knew it was time for us to wander over and take a peek at what had developed. It wasn’t a pretty sight.
The pile of dirt which, ideally, should have been dust dry, was, instead, an oozing mass of mud the consistency of day-old chocolate mousse. The hole which should have been just deep enough to hold the gravel and our yellow submarine was getting no deeper. Instead, it was rapidly getting wider, filling with water, caving in at the edges and creeping toward our future foundation site. Back in March, that flowing river was five feet down. Now it was two feet nearer the surface and eating away our septic hole chunk by eroding chunk. I had visions of our entire building site plus the pasture disappearing into an ever widening sink hole. The yellow submarine would never submerge. It would float forever in the pool rising at our feet.
That night Scott and I kept checking the slowly rising water. By morning the level was steady, and the hole had stopped growing, but it was obvious there was no possible way our new “swimming hole” would ever hold our septic tank. When people came by that day, we offered towels and bathing suits. If they declined, there was still a photo opportunity with the yellow submarine.
In the end, it took extra time and, of course, more money, but Wes found a solution. He pumped out the water, filled in the original hole, brought in a shallower septic tank (more of a black lozenge this time), quickly dug a new hole and got the entire system in without another hitch.