Monday, May 26, 2014

A Small Project

Finally, our three-year turned  five-year plan is drawing to a close. Scott and I often find ourselves looking around our house of straw, wondering how it all happened. Did we really undertake the building of a home, under our own direction? And can it be possible that a moving van will arrive at our Logan house on June 4, load up the belongings we haven't yet moved and whisk everything away to meet us in Torrey? Indeed, the answer is yes, but there are still many things to be completed.

One of those things is the small bathroom in Scott’s office. We had to leave it unfinished (straw and lath walls – just a toilet and a sink) until the end because we needed the plumbing while we were completing the rest of the house. It was the only room that could provide hot water and heated restroom facilities during construction. Now, as moving time draws near, we are reminded of our large project as we repeat it on a much smaller scale in this one room.

It's comforting to begin work in this space, knowing that, this time, we actually know how it should be done.

First I make the straw wall as vertical and flat as possible by removing bulges in the bales.

There is a large hole in one bale, which Scott fills with cob - a thick mixture of clay and straw.

Scott applies slip by hand.















When we plastered the rest of the house, we used a stucco sprayer powered by a compressor. Due to the small size of this bathroom, hand application seemed more appropriate and not very time consuming. Plus, it was much less messy than the sprayer. We were happy with this option since the house is essentially done, and we didn't want to cover our finished walls and floors with new plaster.

Still, we covered the posts and knee braces with painter's tape and plastic to keep mud off of the wood.

Scott applied the scratch coat next, filling in holes in the straw and covering the bamboo poles as he went.

This is the section of wall you see above, but now the large hole is gone and the bamboo is covered.

Using a metal comb (which we call a plaster scratcher), Scott scarifies the finished surface of this first coat of plaster.

This texture, or key, makes it possible for the next coat of plaster to stick to the scratch coat.

 We put finishing touches on the lath around the water pipe and the drain access...

and attach diamond lath to the wall for the pocket door.















The major work of this room is finished. It seems a little strange to say that the "only" things left are applying final plaster coats, painting the walls, covering ceiling with bamboo matting, building a sink cabinet and, finally, reinstalling the sink and toilet. We estimate it will take a week to ten days from this first plaster to the installation of fixtures. A small project indeed.

Saturday, December 29, 2012

Across Four Novembers

From the outside of our house, it has been very apparent that we have made an incredible amount of progress...at least for the first three years. However, when you compare this year’s exterior photo with that of the 2011 photo, the house looks ostensibly the same.
November 2012
November 2011
November 2010
November 2009
But, if you walk inside the house, you'll see a completely different story. This is where we focused most of our efforts in 2012.
November 2011
November 2012
It really is beginning to look like a house instead of a construction site!

Saturday, December 17, 2011

Interior Walls

Now that the weather keeps us indoors, we devote our time to interior work. Some of the projects require two full-time workers - plastering or window trim for example. Other projects require one full-time person (usually Scott) and occasionally a second person (usually me) to hold a piece of wood in place while the other wields the nail gun for a moment or to hold one end of the tape measure while the other reads the smart end. During the off-duty moments, the second person (me) needs to make herself useful, so I’ve been nailing lath to the framing of our interior walls.

Anyone familiar with conventional construction might wonder why in the world we’re using lath. That same person would know that the logical next step to a lath wall is plaster...hence the term “lath and plaster walls.” In today’s construction world, lath and plaster has been mostly replaced with solid drywall which is faster and less expensive to install. But, as we have seen with the change in our construction time line, we apparently are not worried about faster (even though being finished with this house before we’re 60 would be nice). Traditional lath and plaster walls require skilled plasterers to apply three coats of plaster over a framework of lath strips. By the time we are actually finished, we’ll probably be able to hire out as skilled plasters. And, since solid dry wall is, well, solid, it’s not the best material for making curved walls with the handmade look we so admire. Hence the process begins.

During our Thanksgiving stay I was able to put up the lath on one side of the walls separating the main living space of our house from the bedroom and from Scott’s office. We can more easily see the space we will soon be living in.

Looking from the living room into the bedroom
The other side of the same wall
Looking from the bedroom into the living room