Tuesday, February 10, 2015

Finished!

-->
A quick Google search reveals many famous lasts—last call, last words, last meal. And, if you play games of trivia, you might encounter questions like, what was the last state to join the union? Hawaii. Or, what is the last Greek letter? Omega. Or even, what was the last act to perform at Woodstock? Jimi Hendrix.

We are not on any list of famous lasts, but one might ask, what was the last room to be finish? The answer would be the office bathroom. This sequence of completion was due to the fact that, during the interior plaster phase, we needed a bathroom with hot water, a toilet and a sink while we worked on the rest of the house. Even after we received a certificate of occupancy, that little bathroom was a functioning bathroom in every way, unless one counted the one bare straw and three lath walls.  So, last July, we took our last straw bale house step by removing the fixtures and plastering the walls. 

After applying the first two coats, we visited family for a week and then returned to continue work. Since a new plaster layer will not adhere to a dry surface, Scott used our garden sprayer to moisten the walls with water.

The plaster went on beautifully despite the restricted work space. Scott said he felt like had practiced enough on the rest of the house that he now knew how to do it.

Scott used Ultramarine Blue oxide pigment from The Earth Pigments Company in Cortaro, Arizona, to make the paint.

After six years of construction, we had lots of left over materials which we used in this project, plus a few things we bought specifically for it. The mirror was purchased four years earlier from a little antique shop in Scipio, Utah.

The sink (notice the hot and cold handles) came from Habitat for Humanity's ReStore in Salt Lake. It cost a grand total of ten dollars.

The backsplash is left-over bamboo matting used earlier for the ceiling in the kitchen and sun room. The counter top is a piece of cement form used in the foundation of the house. The cement contractor didn't have any forms in the size necessary for our straw bale foundation, so we ended up with a huge stack of cement covered 5/8" plywood. We've used it for a number of things. This particular piece, after foundation work, sat under a pile of straw bales for three years. We just sanded it smooth, stained it with gel coat and applied 6 coats of Varathane.

We salvaged the cabinet door from a load of things our neighbor was sending to the dump. The cabinet itself is made from oak plywood left over from the bookcase we built in the living room.

The rest of the room is a typical bathroom, no need for details, but at last we can say we are done with the house. Now it's on to other projects, some of which involve more plaster and more straw!

Monday, May 26, 2014

A Small Project

Finally, our three-year turned  five-year plan is drawing to a close. Scott and I often find ourselves looking around our house of straw, wondering how it all happened. Did we really undertake the building of a home, under our own direction? And can it be possible that a moving van will arrive at our Logan house on June 4, load up the belongings we haven't yet moved and whisk everything away to meet us in Torrey? Indeed, the answer is yes, but there are still many things to be completed.

One of those things is the small bathroom in Scott’s office. We had to leave it unfinished (straw and lath walls – just a toilet and a sink) until the end because we needed the plumbing while we were completing the rest of the house. It was the only room that could provide hot water and heated restroom facilities during construction. Now, as moving time draws near, we are reminded of our large project as we repeat it on a much smaller scale in this one room.

It's comforting to begin work in this space, knowing that, this time, we actually know how it should be done.

First I make the straw wall as vertical and flat as possible by removing bulges in the bales.

There is a large hole in one bale, which Scott fills with cob - a thick mixture of clay and straw.

Scott applies slip by hand.















When we plastered the rest of the house, we used a stucco sprayer powered by a compressor. Due to the small size of this bathroom, hand application seemed more appropriate and not very time consuming. Plus, it was much less messy than the sprayer. We were happy with this option since the house is essentially done, and we didn't want to cover our finished walls and floors with new plaster.

Still, we covered the posts and knee braces with painter's tape and plastic to keep mud off of the wood.

Scott applied the scratch coat next, filling in holes in the straw and covering the bamboo poles as he went.

This is the section of wall you see above, but now the large hole is gone and the bamboo is covered.

Using a metal comb (which we call a plaster scratcher), Scott scarifies the finished surface of this first coat of plaster.

This texture, or key, makes it possible for the next coat of plaster to stick to the scratch coat.

 We put finishing touches on the lath around the water pipe and the drain access...

and attach diamond lath to the wall for the pocket door.















The major work of this room is finished. It seems a little strange to say that the "only" things left are applying final plaster coats, painting the walls, covering ceiling with bamboo matting, building a sink cabinet and, finally, reinstalling the sink and toilet. We estimate it will take a week to ten days from this first plaster to the installation of fixtures. A small project indeed.

Wednesday, June 19, 2013

Painting with Lime Wash

Once again, we’re arriving at lasts…this time the last exterior paint. This will be applied to the north and south bump-outs. This paint is a lime wash because we applied lime plaster to the bump-outs which have limited protection from precipitation. The questions arises – what color should we use?

On the south bump-out, we selected yellow ocher. We’ve used this color frequently throughout the interior of the house—we must really like it. We chose it for the south bump-out for a specific reason: the intensity of the southern sun. We have noticed that the dark frames of our windows become very hot in the midday sun and cool quickly at night. The thermal expansion and contraction of the frames have caused a small bit of plaster to slough off in several places. A large dark plaster wall would also be subject to increased thermally-induced movement. Therefore, we opted for a light color to minimize the expansion and contraction that occurs during the day and night  and across the seasons. Plus, the dark window frames in the pale yellow wall look fantastic.

Scott repaired the plaster with a commercial concrete patch mix with polymer additive to make it more elastic. He made an expansion joint at each problem area around the frames. Then we covered the south bump-out wall with a paint created from pigments we purchased from Capital Ceramics in Salt Lake City - a mixture of yellow ocher, ceramic brown and raw sienna. In addition to the pigments, the lime wash consisted of one part Type-S lime and three parts water.

 We were uncertain about the color for the north bump-out, so Scott mixed several colors and applied test patches.
We contemplated these for several days and decided upon eggplant (or aubergine in the world of color design). Aubergine is the darkest color in the set.

Two friends – Jean and Catherine - arrived just in time to help with all of the painting. After completing the south wall, they jumped right in on the north wall with three coats of aubergine.

Yikes! It wasn't the ugliest thing we had ever seen, but it wasn't working here. Scott said this color might be nice somewhere...but somewhere far from here. The coats seemed much lighter than the test patch, and, despite all our efforts to smooth things out, we could see every brush stroke. This wouldn’t do at all.  Scott declared that we were going to revert to our tried and true color – yellow ocher.

He mixed the same pigments as before – yellow ocher, ceramic brown and raw sienna with a slightly greater proportion of ceramic brown – and we did the entire wall over again with much better results.
With patience, stick-to-it-iveness and friends, you can do anything.

Final Exterior Plaster

-->
This is destined to be a summer of lasts. Typically lasts and goodbyes are not my favorite moments. I’m much more comfortable with firsts and hellos. However, the lasts of this summer are ones we’ve been looking forward to for a long time.

Take last week for example. We needed to add the very last coat of exterior plaster. If we went by the book, that would have meant ¼ inch of finish coat over the 2nd layer that’s been on the house since last fall. In our case, because our walls have undulations, some of which are significant, that final ¼ inch of plaster has been as great as one inch in some places. Our goal? To make the straightest walls possible while, at the same time, keeping the earthy, hand-made character of a straw bale house that we love so much.

Scott has spent more time with plaster than I have. Here he applies that ¼-inch layer that books talk about.


His small Japanese pool trowel was his favorite tool.

I really got into it.


After four long days of work, that last coat brought the walls to their full depth. As you can see, the windows are now flush with the walls. It looks finished.

I applied the very last handful of plaster.
The exterior plaster is complete. It is a fond farewell. The next step...painting all of the exterior walls.

Saturday, December 29, 2012

Across Four Novembers

From the outside of our house, it has been very apparent that we have made an incredible amount of progress...at least for the first three years. However, when you compare this year’s exterior photo with that of the 2011 photo, the house looks ostensibly the same.
November 2012
November 2011
November 2010
November 2009
But, if you walk inside the house, you'll see a completely different story. This is where we focused most of our efforts in 2012.
November 2011
November 2012
It really is beginning to look like a house instead of a construction site!

Sunday, December 2, 2012

Rain

When we say we are moving to Torrey, most people visualize a hot, dry desert town. We don’t really dispel that perception because, if everyone knew what it is really like, it would be filled with people. Instead, it is a summer tourist town. People from all over the world enjoy its red rock scenery, verdant meadows and nearby alpine forests. Capitol Reef National Park is only a few minutes from town. But once the tourist season passes, the not quite 200 local residents get their sleepy little town back. On late fall days, they can walk down main street and not see even one car pass by.

At an elevation of 6830 feet, one might guess Torrey would be very cold, but winter temperatures range from 0 to 60 degrees, and summer temperatures range from 50 to 90 degrees. Summer has a monsoon season, and you can usually plan on plenty of rain after the 4th of July. Sometimes it is more than plenty of rain.

Rain on a straw bale house is dangerous. It can melt your plaster walls, and, if it gets a chance, it can rot your bales. This is why well-designed straw bale houses have large overhanging eaves protecting the walls. Our deep porch serves this purpose.

We have added two additional features that will keep moisture away from our house. First we created a dry river by grading an 8-inch swale around the house. We then filled the swale with gravel, the idea being that rain water on the roof would be directed to this dry “stream bed” and away from the house. We also hung chains from the rain gutters and buried the ends in gravel-filled holes in the dry river bed. At the base of the chains we stacked flat rocks in such a way as to deflect water running down the chains away from our porch posts.



Often visitors ask about the purpose of the chains. Scott tells them that, because it is so windy in Wayne county, we need a way to hold the house to the ground. Of course, now you know the real story.

Friday, October 26, 2012

We're Almost Home

I’ve always had lofty goals. For this, our fourth building season, I hoped to have the plaster work totally completed - the entire house as well as the garage. We are close.

Here you can see Scott and Jerry working on exterior plaster.


Next summer, the fifth and, one can only hope, last building season, we will put the final coats of plaster on the exterior of the house and all of the garage. That means finish work and landscaping are all that remain.

It’s almost time to call Torrey home.

The Help

Finish plaster. Finish plaster. Finish plaster. This was the mantra of the summer. Now that fall has arrived, I keep walking from room to room in order to convince myself that it really is true. The interior plaster is completely finished. And, thanks to Scott’s experiments and ultimate successes in creating the perfect color palette, the walls are even painted.

Scott's Work Station

Looking From Scott's Work Station to the Storage Area

Looking from the Storage Area to Scott's Work Station
It wouldn’t have been possible without Cali and Jerry. In June, when they arrived in Torrey, they had just completed a straw bale internship at Community Rebuilds in Moab. After an entire summer of day-in and day-out plaster work, they have become true plaster artists.

Cali and Her Last Tree
Jerry's Last Day - Exterior Plaster
Artists always sign their work.

Thursday, October 25, 2012

A Little Help From Our Friends



When Bryan and Jean showed up in Torrey, three times now, it felt as though the Lone Ranger had arrived. But instead of a horse named Silver, he was riding a motorcycle and there were two of him. During their first visit, Jean used her extensive family finance Ph.D. skills to cut burlap. This we attached to the timber frame in order to prevent cracks from developing between the wood posts and the plaster walls. Bryan exercised his previous building experiences installing the sheathing on the south bump out. This sheathing would eventually contain our icynene insulation.

The second time they arrived, they spent their energies painting interior walls, scrubbing plaster from interior posts, wiring outlets, attaching switch and outlet plates, and hanging sheet rock in the kitchen.


Last weekend, once again, they wielded brushes and painted the bedroom closet walls. In addition, they initiated our newly installed shower, and they spirited Scott away from the job site for a hike to a local petroglyph site.

Once again, Scott and I continue to be the beneficiaries of the generosity of friends.

Monday, October 22, 2012

An Homage To Trees

In the four years Scott and I have been building this house, we have also been planting trees: fifteen cottonwoods, five blue spruces, five apple trees, two cherries, one plum, four lindens, two peaches, two apricots, five walnuts and two willows, We have plans for others - red buds, green ash, big-tooth maples, mountain ash -  but we need to finish the exterior plaster and grade the ground around the house before anything more can be planted.

Much of this “reforestation” could be called mitigation for the douglas fir and ponderosa pine that were once standing in neighboring forests. And, even though those trees had already been killed by insects and fire before they found themselves resurrected as the posts and beams supporting our house, it seemed appropriate to recognize the origins of our home’s framework.

This is a beauty of straw bale. Any metaphor one might wish to create, can be written in the details of the finish plaster. Thus, we are surrounded by trees outside and in, an homage to trees...

Entryway Tree
Bedroom Tree
Office Door Tree
Office Bathroom Tree

Monday, August 6, 2012

An Earthen Floor

We have been anticipating the completion of our earthen floor. The dirt and dust has become more and more tiresome, especially in the last few weeks as we see this structure evolve into a house.

Early on our architect explained that the earthen floor would be the very last phase of our project. Why last? Because it takes several weeks to complete the entire process. During that time, and even after it is done, we cannot easily put scaffolds on the floor since they will damage the finish. Still, that dirt is awfully, well, dirty, and like an unwelcome visitor, we are anxious to see it go. Even though the end of construction is at least a year away, we decided the earthen floor could be the last phase of our main living space. A year was too long to wait for dirt to be gone.

To that end, after a big push to finish all of the lath and straw walls in the main living space, we made all of the preparations  necessary  in order to cover our dirt.  We planned to be set up and well organized before our team showed up Monday morning at 9:00. This meant plenty of sifting clay, chopping straw, and mixing, mixing, mixing plaster - 47 loads of it the day before installation. Doug made enough screed boards for everyone to have their own. These boards, the thickness of the finished floor, were designed to be used as guides as the plaster was applied to the floor’s base.

I think Scott had been dreaming about all of the things that could go wrong with this floor since we first decided to put one in our house. I know, the night before floor plaster day, I dreamed of a 45% degree floor covered with boulders which I attempted to plaster all night long. So much for a restful night.

Monday morning John, Linda, Shanna, Doug, Jerry, Cali and I gathered on the dirt for instructions. Scott explained the process and demonstrated the use of the screeds, all the while emphasizing the importance of applying enough pressure to compress the plaster and, at the same time, remove all air gaps. This would help prevent cracking in the floor.

Everyone set to work at the south window, forty-seven loads of plaster arrayed behind them. Shanna and I manned the mortar mixer and refilled empty tubs as quickly as they appeared. Seven and a half hours later, with a total of 69 loads of plaster smoothed before us, we toasted a successful floor installation and cheered the end of dirt.

Scott levels the floor before plaster is applied.
The rented mortar mixer that did the heavy lifting for two days.

Tubs of plaster awaiting application.
The team begins plastering the floor.
Halfway finished.

 Scott hard trowels the floor after it begins to dry.
The first step of the floor is now finished. Over the next several weeks we will apply a plaster paint then many coats of linseed oil to complete the process.